- Preparation of the TOR and cost estimate | √ – 10.02.2019
- TOR and cost estimate submission to ADB | √ 12.02.2019
- Review and approval of the TOR and cost estimate | √ 14.02.2019 – NoL
- Advertisement and request for EOI | √ 12.03.2019
- Submission of EOI by consultants | √ 10.04.2019
- Shortlisting and submitting of Submission 1 | √ 22.04.2019 – Surat Pengantar – Cost Estimate – Minutes of CSC Shortlistig Meeting – Statement of Ethical Conduct – Request for Proposal – Narrative Evaluation Criteria – Evaluation EOI – Narative Evaluation EOI – Shortlisting and RFP for QCBS
- Review and approval of submission 1 | √
28.04.201922 .07. 2019 – NoL - Issue RFP to shortlisted firms | √
30.04.2019
- Submission 2 of proposals by consultants |
14. 06.201914.09. 2019 - Technical proposal evaluation and Submission 2 |
05.07.201905.10.2019
- Review and approval of Submission 2 |
15.07.201915.10.2019 – NoL
- Opening and evaluating financial proposals and submit Submission 3 |
22.07.201922.10.2019
- Review and approval of Submission 3 |
27.07.201927.10.2019 -NoL
- Contract negotiation |
06.08.201906.11.2019 - Winner appointment (internal MORTHE’s procedure)* |
30.08.201930.11.2019
- Signing of contract (including standstill/objection period) |
07.09.201908.12.2019
- Copy of contract sent to ADB |
08.09.201909.12.2019
- Issuance of PCSS number |
12.09.201913.12.2019